Table 2. Summary of logging activities at Site 1186
Date (Oct, 2000)
|
Time (local)
|
Logging Activity
|
27
|
2130
|
Hole preparation (including flush with sepiolite) complete,
rig wireline. |
|
2305
|
Run geophysical tool string into hole. |
28
|
0105
|
Reach bottom of hole. |
|
0225
|
Finish uplog at 274 m/hr from 1034 mbsf to 679 mbsf. |
|
0255
|
Resume logging at 163 mbsf below base of pipe. |
|
0330
|
Finish uplog at 274 m/hr from 163 mbsf to 16 m above seafloor.
Pull out of hole. |
|
0430
|
Recover geophysical tool string, begin preparing FMS/Sonic tool
string. |
|
0615
|
Run FMS/Sonic tool string into hole. |
|
0750
|
Reach bottom of hole. Start uplog from 1033 mbsf. |
|
0815
|
Tool string goes dead at 948 mbsf; reinitialized and run back
to bottom of hole. |
|
0940
|
Finish uplog at 274 m/hr from 1033 to 690 mbsf. Lower toolstring
for second pass. |
|
1108
|
Finish second uplog at 274 m/hr from 1033 to 975 mbsf. Pull
out of hole. |
|
1215
|
FMS/Sonic tool string on deck. |