Temperature Data Processing
ODP logging
contractor: LDEO-BRG
Hole: 1239A
Leg: 202
Location: Carnegie Ridge (equatorial SE Pacific)
Latitude: 0°40.32'S
Longitude: 82°04.85'W
Logging date: May 12-13, 2002
Bottom felt: 1424.5 mbrf (used for depth shift to sea floor)
Total penetration: 517 mbsf
Total core recovered: 515.10m (99.9%)
Temperature
Tool Used: LDEO-TAP
Depth versus time recording available: No depth data recorded.
Logging
Runs
Logging string 1: DIT/HLDT/APS/HNGS/TAP/MGT
Wireline heave compensator was used to counter ship heave.
The TAP tool acquires borehole temperature, tool acceleration, and hydrostatic pressure. It may be run in either memory mode, where the tool is fastened to the bottom of logging string and data is stored in the on-board memory, or in telemetry mode, where the tool is run alone and data is recorded in real-time by the third-party data acquisition system. When the tool is run in memory mode, the stored data is dumped to the third party data acquisition system upon the tool's return to the rig floor.
Borehole fluid temperature is recorded with one thermistor located at the bottom of the tool. The internal temperature of the tool is recorded as well. A pressure transducer is included to turn the tool on and off at specified depths when used in memory mode. Typically, data acquisition is programmed to begin 100 m above the seafloor. A 3-axis accelerometer is also included to measure tool movement down hole. These data are expected to be instrumental in analyzing the effects of heave on a deployed tool string which will lead to the fine tuning of the WHC (wireline heave compensator).
Drilling and circulation operations considerably disturb the temperature distribution inside the borehole, thus preventing equilibrated temperature conditions. The amount of time elapsed between the end of drilling fluid circulation and the beginning of logging operations is not long enough to allow the borehole to recover thermally.
Depth = BD *(Pressure-MudlineP) / (Pmax- MudlineP)
where
Depth = mbsf
BD = bottom depth (mbsf)
Pressure = bars
Mudline P = bars
Pmax = pressure at bottom depth (bars)
This procedure does not fully account for the vagaries of the pressure readings that result in lots of ups and downs in the generated depth channel. Further problems arise because of pumping during logging operations, which affects the pressure, especially when the Side Entry Sub is used. Also, whenever heavy pills of mud are used, the pressure-depth calculation is affected, resulting in a non-linear effect that is difficult to account for.
The following processing has been performed at Hole 1239A:
Logging Run: DIT/APS/HLDT/HNGS
Mudline P=142.8 bars
Pmax= 198 bars at 517 mbsf
Depth = 517*(Pressure - 142.8)/(198 - 142.8)
Gilles Guerin
phone: 845-365-8671
fax: 845-365-3182
email: Gilles Guerin
Cristina Broglia
Phone: 845-365-8343
Fax: 845-365-3182
E-mail: Cristina Broglia